One of the most common questions homeowners ask before starting a bathroom renovation is "how long will it take?" The short answer: a straightforward bathroom installation takes 3-7 working days, while a complex renovation can take 10-14 days or more. But the real answer depends entirely on the scope of your project, the condition of the existing bathroom, and how well-prepared you are before work starts.

This guide gives you realistic timelines for every type of bathroom project, a day-by-day breakdown of what happens during a typical renovation, and — perhaps most usefully — an honest look at what causes overruns and how to avoid them.

Timeline by Project Type

Project Type Typical Duration Notes
Like-for-like suite replacement 2-3 days Same layout, just new toilet, basin, and bath/shower. Minimal tiling.
Full renovation, same layout 5-7 days Strip out, re-tile walls and floor, new suite, new shower. No plumbing repositioning.
Full renovation with layout change 7-10 days Moving toilet, basin, or shower positions. New drainage runs, possible joist work.
Wet room installation 7-10 days Floor grading, full tanking, and curing time add 2-3 days over a standard renovation.
En-suite from scratch 10-14 days Building the room (stud walls, door), running plumbing and electrics from scratch, full fit-out.

Important: These timelines assume one fitter (or a fitter plus one subcontractor) working full days. If your fitter is juggling other jobs and only coming 3-4 days a week, a 7-day job can stretch to 2-3 weeks. Confirm their availability upfront.

Day-by-Day: What Happens During a Full Bathroom Renovation

Here is a typical schedule for a standard full bathroom renovation (same layout, new everything), which usually takes 5-7 working days:

Day 1: Strip Out

The old bathroom comes out. The fitter removes the existing suite (toilet, basin, bath or shower), strips tiles from walls and floor, and removes any rotten or damaged plasterboard. The room is taken back to bare walls and floor, and the existing pipework is exposed. Waste is removed or bagged for skip collection. By the end of day one, you are looking at an empty shell.

Day 2: First Fix Plumbing and Electrical

The plumber routes new hot and cold water pipes to the correct positions for the new suite layout. If there is a concealed shower valve, the pipework for that is installed behind the wall. The electrician (if needed) runs cables for the extractor fan, any new lighting, and the shower isolator switch. If the walls need re-boarding (new plasterboard or cement board for wet areas), that happens today too.

Day 3: Plastering and Preparation

If the walls need skimming, the plasterer comes in. Fresh plaster needs time to dry before tiling — typically 24-48 hours depending on ventilation, temperature, and the thickness of the skim coat. In some cases, the fitter will use tile backer boards instead of plaster, which can be tiled immediately and eliminates this waiting period. Floor preparation (levelling compound, plywood overlay) also happens today.

Days 4-5: Tiling

This is usually the longest phase. The tiler works through the walls first (starting from the bath or shower area), then the floor. Tiling cannot be rushed — each row needs to be level and set before the next one goes on, and complex cuts around pipes, windows, and fixtures take time. Large-format tiles look stunning but require more precision and slower work than smaller tiles.

Day 6: Second Fix Plumbing

With the tiling complete, the plumber returns to connect the suite. The toilet, basin, taps, and shower are all fitted and connected. The bath (if applicable) is positioned and plumbed. The heated towel rail is connected (either to the central heating or wired in as electric). Everything is tested for leaks, flow, and drainage.

Day 7: Finishing and Snagging

Grouting is completed (some tilers grout as they go, others do it as a final step). All silicone sealing is applied — around the bath, shower tray, basin, and wall-to-floor junctions. Accessories are fitted: mirror, toilet roll holder, towel hooks, shower screen. A thorough clean-up, and then a walkthrough with you to identify any snagging items.

What Causes Overruns (And How to Minimise Them)

Most bathroom renovations that overrun do so because of foreseeable issues that could have been prevented with better planning. Here are the main culprits:

1. Materials Arriving Late

This is the single most preventable cause of delays. If tiles arrive halfway through the tiling phase, or the shower valve is back-ordered, work stops — but your fitter's daily rate does not.

Solution: Order everything before work starts. Every tile, every fixture, every accessory. Have it all on site (or confirmed for same-day delivery) before the strip-out begins. Allow extra tiles (10-15% overage for cuts and breakages).

2. Hidden Problems

Once you strip back an old bathroom, you sometimes discover problems that were invisible before:

How to prepare: Build a contingency of 10-20% into both your budget and your expected timeline. Discuss with your fitter upfront how they handle unexpected problems — specifically, how they communicate the issue, agree extra costs, and adjust the schedule.

3. Tiling Taking Longer Than Expected

Tiling is consistently the phase that overruns. It is physical, precision work that cannot be rushed without compromising quality. Factors that slow tiling down:

4. Waiting for Plaster to Dry

If walls need replastering (which is common after stripping old tiles), the new plaster must dry to the correct moisture content before tiles can be applied. Tiling onto wet plaster causes adhesive failure — the tiles will eventually come loose.

Drying time depends on: Room temperature, ventilation, time of year (winter takes longer), and plaster thickness. A typical bathroom skim coat needs 24-48 hours minimum, but can take longer in cold or humid conditions.

The workaround: Tile backer boards (cement board or foam board) can be fixed to the walls instead of plastering. These are waterproof, perfectly flat, and can be tiled immediately. They cost slightly more in materials (£5-£8/m2 for the boards plus fixings) but save a day or more of waiting. Many modern bathroom fitters use them as standard.

5. Subcontractor Scheduling

If your fitter uses subcontractors (a separate tiler, electrician, or plasterer), the job depends on all of them being available at the right time. If the electrician cannot come on Day 2 and is only available on Day 5, the entire schedule shifts.

Solution: Ask your fitter at the quote stage how they manage subcontractor scheduling. The best fitters have established relationships with regular subcontractors who prioritise their work. If a fitter tells you they will "book the electrician once we start," that is a risk — it should be booked before work begins.

Living Without a Bathroom

The practical reality of a bathroom renovation is that you will be without a working bathroom for some or all of the project. Here is how to manage it:

If It Is Your Only Bathroom

If You Have a Second Bathroom

Life is considerably easier if you have a second bathroom or en-suite. The main challenge becomes dust and noise rather than access to facilities. Ask your fitter to seal the door with dust sheets and use a dust extraction system when cutting tiles.

Timing Tips

Questions to Ask Your Fitter About Timeline

Before committing, ask these timeline-specific questions:

  1. How many working days will the job take? (Not calendar days — working days.)
  2. Will you be here every working day until completion? (Or will you be splitting time with another job?)
  3. What time will you start and finish each day? (Most fitters work 8am-4pm or 8:30am-5pm.)
  4. What could cause the job to overrun, and how would you handle it?
  5. When will I have a working toilet reconnected?
  6. Are all subcontractors already booked for the right days?

A fitter who answers these confidently and specifically has done this before and knows how to manage a project. Vague answers ("it depends," "we will see how it goes") suggest less experience or less commitment to your timeline.

Ready to Plan Your Bathroom Renovation?

The best way to get an accurate timeline for your specific project is to have a fitter visit, assess the space, and provide a detailed schedule alongside their quote. Fill in the form below to receive free quotes from experienced local bathroom fitters.

Get Your Free Bathroom Quote

Tell us about your project and we will connect you with trusted local fitters.